CUET PG PYQs for Project Management with Solutions: Practice CUET PG Previous Year Questions

Sahaj Anand's profile photo

Sahaj Anand

Content Writer | Journalism Graduate | Updated on - Dec 17, 2025

Project Management is an important topic in the Water Engineering and Management section in CUET PG exam. Practising this topic will increase your score overall and make your conceptual grip on CUET PG exam stronger.

This article gives you a full set of CUET PG PYQs for Project Management with explanations for effective preparation. Practice of CUET PG Water Engineering and Management PYQs including Project Management questions regularly will improve accuracy, speed, and confidence in the CUET PG 2026 exam.

Also Read

CUET PG PYQs for Project Management with Solutions

  • 1.
    The process of raising capital to carry out various activities in marketing is called

      • Risk bearing
      • Financing
      • Grading
      • Standardization

    • 2.
      Providing small loans that are repaid within short periods of time used by low income individuals is called

        • Credit
        • Microfinance
        • Capital
        • Bonus

      • 3.
        Arrange the steps in sequential manner as followed for Programme Evaluation and Review Technique (PERT).
        A. Planning
        B. Organising
        C. Scheduling
        D. Coordinating and Controlling
        Choose the correct answer from the options given below:

          • A, B, C, D
          • A, C, B, D
          • B, A, D, C
          • C, B, D, A

        • 4.
          What will be the expected time for driving the precast piles for a bridge abutment activity having optimistic time 22, most likely time 30, and pessimistic time 50?

            • 34 days
            • 32 days
            • 42 days
            • 40 days

          • 5.
            If 'A' is the optimistic time, 'B' is the pessimistic time and 'C' is the most likely time of an activity, then the expected time of activity is:

              • \( \frac{A+4B+C}{6} \)
              • \( \frac{4A+B+C}{6} \)
              • \( \frac{A+B+4C}{6} \)
              • \( \frac{4A+4B+C}{6} \)

            • 6.
              Earliest finish of an activity is always:

                • Less than earliest event of the following node
                • Greater than earliest event of the following node
                • Less than or equal to earliest event of the following node
                • Greater than or equal to earliest event of the following node

              • 7.
                Arrange the following elements of a feedback control loop in the correct order: (A) Actuator (B) Error detection (C) Controller (D) Feedback sensor Choose the correct answer from the options given below:

                  • (B), (C), (A), (D)
                  • (A), (C), (B), (D)
                  • (B), (A), (D), (C)
                  • (C), (B), (D), (A)

                • 8.

                  Match the LIST I with LIST II 

                  LIST-ILIST-II
                  A. Retail marketI. Books
                  B. Local marketII. World Trade Organization
                  C. World marketIII. Final consumers
                  D. Capital marketIV. Village


                  Choose the correct answer from the options given below:

                    • A - I, B - II, C - III, D - IV
                    • A - I, B - III, C - II, D - IV
                    • A - III, B - IV, C - II, D - I
                    • A - III, B - I, C - IV, D - II

                  • 9.
                    The reduction in project time normally results in

                      • Increasing the direct cost and decreasing the indirect cost
                      • Decreasing the direct cost and increasing the indirect cost
                      • Increasing the direct cost and the indirect cost both
                      • Decreasing the direct cost and the indirect cost both