Project management techniques e.g. PERT, CPM etc. is an important topic in the Civil Structural and Transport Engineering section in CUET PG exam. Practising this topic will increase your score overall and make your conceptual grip on CUET PG exam stronger.
This article gives you a full set of CUET PG PYQs for Project management techniques e.g. PERT, CPM etc. with explanations for effective preparation. Practice of CUET PG Civil Structural and Transport Engineering PYQs including Project management techniques e.g. PERT, CPM etc. questions regularly will improve accuracy, speed, and confidence in the CUET PG 2026 exam.
Also Read
CUET PG PYQs for Project management techniques e.g. PERT, CPM etc. with Solutions
1.
Which of the following is the "amount of time" by which the "start of an activity" may be delayed without delaying the "start of a following activity"?- Interference float
- Free float
- Independent float
- Total float
2.
Which of the following statements (pertaining to CPM network analysis) are correct?
A. It is an event-oriented method.
B. It is an activity-oriented method.
C. Time and cost are controlling factors.
D. Time alone is the controlling factor.
Choose the most appropriate answer from the options given below:- A and B only
- A and D only
- B and C only
- C and D only
3.
The time estimates obtained from four contractors (P, Q, R and S) for executing a particular job are as under:
\[\begin{array}{|c|c|c|c|} \hline \textbf{Contractor} & \textbf{Optimistic time, $t_o$} & \textbf{Most likely time, $t_m$} & \textbf{Pessimistic time, $t_p$} \\ \hline \text{P} & 5 & 10 & 13 \\ \hline \text{Q} & 6 & 9 & 12 \\ \hline \text{R} & 5 & 10 & 14 \\ \hline \text{S} & 4 & 10 & 13 \\ \hline \end{array}\]
Which of these contractors is more certain about completing the job in time?
- P
- Q
- R
- S