CAT MCQs on Time and Work: CAT Questions for Practice with Solutions

Chanpreet Kaur's profile photo

Chanpreet Kaur

Content Writer | MBA Professional | Updated on - Nov 26, 2025

The CAT QA section requires speed and accuracy, along with a thorough understanding of the Time and Work. This article provides a set of MCQs on Time and Work to help you understand the topic and improve your problem-solving skills with the help of detailed solutions by ensuring conceptual clarity, which will help you in the CAT 2025 exam preparation

Whether you're revising the basics or testing your knowledge, these MCQs will serve as a valuable practice resource.

The CAT 2025 exam is expected to follow a similar trend to the CAT 2024, with 22 questions from the QA section out of a total of 68 questions.

Also Read

CAT MCQs on Time and Work

1. Trains A and B start traveling at the same time towards each other with constant speeds from stations X and Y, respectively. Train A reaches station Y in 10 minutes while train B takes 9 minutes to reach station X after meeting train A. Then the total time taken, in minutes, by train B to travel from station Y to station X is
A

15

B

12

C

6

D

10

View Solution


2. John takes twice as much time as Jack to finish a job. Jack and Jim together take one-thirds of the time to finish the job than John takes working alone. Moreover, in order to finish the job, John takes three days more than that taken by three of them working together. In how many days will Jim finish the job working alone?
[This Question was asked as TITA]
A
3
B
4
C
6
D
9

View Solution


3. A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time? [This Question was asked as TITA] 
A
10
B
40
C
50
D
60

View Solution


4. The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number of days Sunil will take to finish the job working alone, is [This question was asked as TITA]
A
27
B
23
C
25
D
20

View Solution


5. At their usual efficiency levels, A and B together finish a task in 12 days. If A had worked half as efficiently as she usually does, and B had worked thrice as efficiently as he usually does, the task would have been completed in 9 days. How many days would A take to finish the task if she works alone at her usual efficiency?
A
24
B
18
C
12
D
36

View Solution


6. Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?
A
10
B
12
C
13
D
14

View Solution


7. A cyclist leaves A at 10 am and reaches B at 11 am. Starting from 10:01 am, every minute a motor cycle leaves A and moves towards B. Forty-five such motor cycles reach B by 11 am. All motor cycles have the same speed. If the cyclist had doubled his speed, how many motor cycles would have reached B by the time the cyclist reached B?
A
23
B
20
C
15
D
22

View Solution


8. John jogs on track A at 6 kmph and Mary jogs on track B at 7.5 kmph. The total length of tracks A and B is 325 metres. While John makes 9 rounds of track A, Mary makes 5 rounds of track B. In how many seconds will Mary make one round of track A?
A
48
B
38
C
45
D
22

View Solution


9. Anil alone can do a job in 20 days while Sunil alone can do it in 40 days. Anil starts the job, and after 3 days, Sunil joins him. Again, after a few more days, Bimal joins them and they together finish the job. If Bimal has done 10% of the job, then in how many days was the job done?
A
14
B
13
C
15
D
12

View Solution


10. John gets Rs 57 per hour of regular work and Rs 114 per hour of overtime work. He works altogether 172 hours and his income from overtime hours is 15% of his income from regular hours. Then, for how many hours did he work overtime?
A
12
B
14
C
15
D
21

View Solution


11. At what exact time between 3:00 PM and 4:00 PM do the hour and minute hands of a standard clock coincide?
A
3:18:27 PM
B
3:08:14 PM
C
3:09:07 PM
D
3:12:06 PM

View Solution


12. A factory produces a certain number of toys in a week using a team of 40 workers who work for 8 hours daily. Due to an increase in demand, the factory needs to double the production while maintaining the same work schedule. How many additional workers should be hired?
A
44
B
40
C
38
D
36

View Solution


13. ‘A’ while working 40% more efficiently can complete a piece of work in 25 days and ‘B’ while working 25% more efficiently can complete the same work in 21 days. While working with their original efficiencies ‘A’ and ‘B’ together worked for 9 days, then find the time taken by ‘A’ alone to complete the remaining work with his original efficiency.
A
7 days
B
14 days
C
12 days
D
6 days\r

View Solution


14. An overhead water tank of 7200 m3 capacity is being filled with water. The delivery of the pump filling the tank is 5/6th of the delivery of the pump discharging the same tank. As a result, 24 minutes more is needed to fill the tank than discharge it. Determine the delivery of the pump in filling the tank.
A
90 m3/min
B
72 m3/min
C
60 m3/min
D
50 m3/min

View Solution


15. X, Y, Z and W can do a certain piece of work in 10, 15, 25 and 30 days respectively. All of them started the work together but X left the job 2 days before the completion of work, Z left the work 1 day before completion of work, W worked with double of his efficiency. Find total time taken by them to complete the work is how much more or less than the total time taken by X alone to complete the work.
A
\(\frac{223}{41}\) days
B
\(\frac{224}{41}\) days
C
\(\frac{225}{41}\) days
D
\(\frac{226}{41}\) days

View Solution


CAT Questions

  • 1.
    A and B can complete a work in 12 days, B and C in 15 days, and A and C in 20 days. How long will A alone take to complete the work?

      • 20 days
      • 24 days
      • 30 days
      • 36 days

    • 2.
      A tank is emptied everyday at a fixed time point. Immediately thereafter, either pump A or pump B or both start working until the tank is full. On Monday, A alone completed ?lling the tank at 8 pm. On Tuesday, B alone completed filling the tank at 6 pm. On Wednesday, A alone worked till 5 pm, and then B worked alone from 5 pm to 7 pm, to fill the tank. At what time was the tank ?lled on Thursday if both pumps were used simultaneously all along?

        • 4:36 pm
        • 4:12 pm
        • 4:24 pm
        • 4:48 pm

      • 3.

        What is the value of $2^{100} \mod 5$? 
         

          • 1
          • 2
          • 3

          •  


        • 4.
          A pipe fills a tank in 8 hours, another empties it in 12 hours. If both are opened, how long to fill?

            • 24 hours
            • 18 hours
            • 16 hours
            • 20 hours

          • 5.
            A pipe fills a tank in 6 hours. Another pipe fills it in 8 hours. How long to fill the tank together?

              • 3.43 hours
              • 3.53 hours
              • 3.63 hours
              • 3.73 hours

            • 6.
              Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?

                • 13.5
                • 11
                • 12
                • 14.5

              Fees Structure

              Structure based on different categories

              CategoriesState
              General2400
              sc1200
              pwd1200

              In case of any inaccuracy, Notify Us! 

              Comments


              No Comments To Show